Dumps of C_IBP_2305 Cover all the requirements of the Real Exam


SAP C_IBP_2305 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Key Figures & Attributes
  • Optimize inventory in the supply chain utilizing algorithms that derive inventory targets
Topic 2
  • General Configuration of a Planning Area
  • Create and use key figures and attributes to model the supply chain
Topic 3
  • Configure supply planning, run various solvers to generate planning results
  • Use the Fiori Launchpad to customize the UI, work with Excel UI
Topic 4
  • Create and transform forecasts in your planning model
  • Display, create, copy, edit, check, and activate a planning area
Topic 5
  • Define and view information with user-defined charts and dashboards
  • Configure and use Planning Operators to automate processes in your planning model

 

NEW QUESTION # 11
Which features apply to quota violations modeled with the optimizer?

  • A. The optimizer will only violate quotas if quotas are maintained as time-dependent key figures.
  • B. Because quota violations shouldn't be possible, the non-delivery cost rate is less than quota violation cost.
  • C. Quotas can be modeled for sourcing location, production, and consensus demand.
  • D. Min and Max Quotas have to be the same as sourcing ratios.

Answer: B


NEW QUESTION # 12
Using the import/export functionality means working with groups of items that are organized into collections.What is the best practice for managing collections?

  • A. Configuration items should be bundled in the collections based on the SAP IBP project stream.
  • B. You should delete collections after they have been transported.
  • C. A planning area with the copy operators assigned must be bundled in one collection.
  • D. A planning area with its time profile must be bundled in one collection.

Answer: C,D


NEW QUESTION # 13
What does ABC/XYZ segmentation allow you to do?Note: There are 2 correct answers to this question.

  • A. Identify inventory items that require closer attention.
  • B. Substitute missing values in case of sporadic demands.
  • C. Choose time-independent key figures as segmentation measures.
  • D. Use forecasting algorithms that are specific to seasonal demands of SKUs in the segment "B".

Answer: A,C


NEW QUESTION # 14
You are developing the functionality and appearance of the Excel UI for SAP IBP business users.Which extensibility capabilities for SAP IBP, add-in for Microsoft Excel are provided by Custom VBA coding?Note:
There are 2 correct answers to this question.

  • A. Changing the layout of the master data workbooks
  • B. SAP IBP ribbon extension
  • C. Changing the entries from the Name Manager
  • D. Changing the member names

Answer: A,B


NEW QUESTION # 15
You created a key figure and want to add calculations.Which of the following rules do you consider?Note: There are 2 correct answers to this question.

  • A. Key figures can be calculated across different planning levels.
  • B. The calculation chain for a key figure must always result in a calculated key figure.
  • C. All key figure calculations have calculation inputs, which can be marked as stored or calculated.
  • D. Aggregation calculations using SUM or MAX functions must be based on a higher aggregation level.

Answer: A,C


NEW QUESTION # 16
Which constraints are taken into account by the Time-Series-Based Supply Planning Heuristic (Infinite)?Note:
There are 3 correct answers to this question.

  • A. Maximum lot size
  • B. Transportation lead times
  • C. Adjusted transport receipts
  • D. Minimum lot size
  • E. Aggregated constraints

Answer: A,B,C


NEW QUESTION # 17
Which constraints are taken into account by the Time-Series-Based Supply Planning Heuristic (Infinite)?Note: There are 3 correct answers to this question.

  • A. Maximum lot size
  • B. Transportation lead times
  • C. Adjusted transport receipts
  • D. Minimum lot size
  • E. Aggregated constraints

Answer: A,B,C


NEW QUESTION # 18
What are the S&OP operator (optimizer) parameters associated with demand fair share?

  • A. Number of fair share segments Additional tiering costs (default) Number of fair share segments late delivery
  • B. Number of fair share segments Additional tiering costs (default) Inventory days of supply
  • C. Number of fair share segments Additional tiering costs (default) Maximum inventory
  • D. Number of fair share segments Maximum days of coverage Number of fair share segments late delivery

Answer: A


NEW QUESTION # 19
You need to use your resource cost effectively with a certain minimum use, even if it means producing more than demand.Which solutions would apply to this scenario?Note: There are 2 correct answers to this question.

  • A. Balance can be achieved between excessive prebuild and minimum use by incorporating violation costs.
  • B. Capacity leveling will be possible for production and storage resources.
  • C. Excess stock can be generated and will need to be staged in an overflow warehouse.
  • D. Minimum capacity utilization will result in pull production occurring.

Answer: A,C


NEW QUESTION # 20
Which type of Master Data will be represented by the Master Data Type LOCATIONFR?

  • A. Virtual Master Data Type
  • B. External Master Data Type
  • C. Reference Master Data Type
  • D. Compound Master Data Type

Answer: C


NEW QUESTION # 21
Which of the following data can be tracked using a change-history-enabled key figure?Note: There are 3 correct answers to this question.

  • A. Scenario ID
  • B. Key figure type
  • C. Attributes
  • D. Reason code
  • E. Modified date

Answer: C,D,E


NEW QUESTION # 22
Safety Stock outputs from Multistage Inventory Optimization are sent to which of these processes? Note:
There are 2 correct answers to this question.

  • A. Decoupling Points determination in SAP IBP for demand-driven replenishment
  • B. Supply Heuristics in SAP IBP for sales and operations
  • C. Charts creation in SAP Supply Chain Control Tower
  • D. Demand Sensing with Gradient Boosting (Full)

Answer: B,D


NEW QUESTION # 23
What are the ways to achieve rolling aggregation with SAP IBP?

  • A. Using a attribute as a key figure
  • B. Using a local member
  • C. Using a key figure calculation
  • D. Using a appropriate period weight factor

Answer: D


NEW QUESTION # 24
Which pre-processing steps can be used to cleanse historical sales data before generating a statistical forecast in SAP IBP?Note: There are 2 correct answers to this question.

  • A. Bias Detection and Correction in Sales History
  • B. Substitute Missing with Mean or Median in Sales History
  • C. Promotion Sales Lift Elimination
  • D. Intermittency Detection and Correction in Sales History

Answer: B,C


NEW QUESTION # 25
SAP IBP ensures interoperability with which applications?Note: There are 2 correct answers to this question.

  • A. Business Network in SAP Ariba
  • B. Financial Planning in SAP Analytics Cloud
  • C. Salesforce Sales Cloud
  • D. User management in SAP Success Factors

Answer: A,B


NEW QUESTION # 26
Time profiles are made out of levels, and levels are made out of periods.Which ways can SAP IBP identify profiles and periods?Note: There are 2 correct answers to this question.

  • A. Periods are identified by an integer and profiles by an alphanumeric prefix.
  • B. Both periods and profiles have start and end dates.
  • C. Periods are identified by an alphanumeric prefix and profiles by an integer.
  • D. Both periods and profiles are identified by a unique integer.

Answer: A,C


NEW QUESTION # 27
You are modeling a new product introduction.Which of the following steps can be part of your modeling process in the Manage Product Lifecycle app?Note: There are 2 correct answers to this question.

  • A. Create planning objects for new combinations in the app
  • B. Enter the product family to which the new product belongs
  • C. Copy the launch dimension from the reference product to the new product
  • D. Enter the Phase-out Start Date and Phase-out End Date

Answer: A,C


NEW QUESTION # 28
Which applications are present in the sample model SAPIBP1?Note: There are 3 correct answers to this question.

  • A. Inventory Optimization
  • B. Demand Sensing
  • C. Sales and Operations Planning
  • D. Response Planning
  • E. Demand Driven Replenishment

Answer: A,B,C


NEW QUESTION # 29
You create a planning filter using an SAP IBP Fiori app.Which of the following objects can it be applied to?Note: There are 2 correct answers to this question.

  • A. Snapshot operator in the SAP IBP add-in for Microsoft Excel
  • B. Planning view templates in the SAP IBP add-in for Microsoft Excel
  • C. Supply chain graph in Supply Chain Network app
  • D. Jobs in the Applications Jobs app

Answer: B,D


NEW QUESTION # 30
You need to make manual adjustments to your S&OP plan.Which are possible ways of making these changes?Note: There are 2 correct answers to this question.

  • A. Using Driver-Based planning
  • B. Leveraging the functionality of SAP Workzone
  • C. Using Microsoft Excel planning views
  • D. Leveraging the web-based planning capability

Answer: C,D


NEW QUESTION # 31
You are adding a value-based filter to a planning view.Which of the following conditions apply?Note: There are 3 correct answers to this question.

  • A. You can add (or delete) planning objects to a planning view after these filters are applied.
  • B. You can only apply one value-based filter per planning view.
  • C. These filters can be used together with attribute totals in the same planning view.
  • D. The alerts dashboard is not available if a value-based filter is set for the open planning view.
  • E. These filters are always applied based on the values stored in the database.

Answer: B,D,E


NEW QUESTION # 32
You are starting a new implementation project for SAP IBP and are considering the possible system architecture.What are the possible approaches for setting up the system landscape?Note: There are 2 correct answers to this question.

  • A. Set up a three-tier landscape using transport, starting from the development system to test and production.
  • B. Create additional test planning areas in the production system to support cutover needs.
  • C. Create additional planning areas in the test system to support training needs.
  • D. Set up a two-tier landscape, and have the configuration of the development system regularly updated from the production system.

Answer: A,D


NEW QUESTION # 33
You need to create time periods for the time profile in a planning area.What should you be aware of when running the Create Time Periods application job?

  • A. A time profile has to be activated so that the application job can proceed.
  • B. In the Parameter Section of the application job, choose the Time Profile ID and Planning Area.
  • C. The assigned Planning Area must be active.
  • D. This application job can be run for multiple time profiles at once.

Answer: B


NEW QUESTION # 34
Model configuration allows the attributes of a master data type to be assigned as key figures.Which features are relevant for this type of object?

  • A. This object provides a single value for a unique planning combination.
  • B. This type of key figure is not usually stored and it cannot be set to editable.
  • C. This object contains user-defined criteria that monitor the running of business plans.
  • D. This object is not exposed to the user in planning views or modeling.

Answer: A


NEW QUESTION # 35
......